I'm trying to create a formula that adds % complete divided by the number of activities where all activities should be completed in 7 months.
Example
Activity 1 - 100% (month1) 75% (month2) 35% (Month3) Not started all other months
Activity 2 - Not started until month 4 - 25% - not started other months
Activity 3 - 100%(month1) 25% (month2), not started all other months
Activity 4 - does not start until month 7